9.6 Sealing Chute
Ⅰ Major Items
9.6.1 Countersunk screws fixing the sealing chute shall be lower than sliding surface of the chute.
Quantity checked:All.
Checking method:Check by observation.
9.6.2 Reserved gaps of respective parts in sealing chute for thermal expansion shall meet the requirements of design technical documents.
Quantity checked:All.
Checking method:Check installation quality records or by field tests.
Ⅱ General Item
9.6.3 Allowable deviation of sealing chute installation shall be in accordance with those specified in Table 9.6.3.Refer to Figure 9.6.3.
Quantity checked:All.
Checking method:Refer to 9.6.3.
Table 9.6.3 Allowable deviation of sealing chute installation(mm)


Figure 9.6.3 Elevation measurement of sealing chute
1-Pallet rail;2-Sealing chute;3-Longitudinal center line of traveling grate equipment;4-Special sample rod for rail